What are the options for electrifying industrial steam?

There are five main options, and they differ mainly in what has to be built around the boiler rather than in the boiler itself.

A direct electric boiler follows the steam load in real time. It needs a grid connection and transformers sized to peak steam demand, it is exposed to peak capacity charges (the part of the electricity bill that depends on maximum import rather than total consumption), and on sites with a high degree of electrification it cannot earn flexibility revenue.

An electric boiler with a lithium-ion battery adds the ability to buy electricity when it is cheap and to earn flexibility revenue, and the battery can be used for loads other than heat. The costs are a larger footprint (a boiler and a battery compound), two sets of transformers and controls, a battery that loses capacity with cycling and is typically expected to need replacement at least once over a 20-year boiler life, and a fire risk that your insurer will price.

An electric boiler with a steam accumulator can supply a few minutes of extra steam from a large high-pressure vessel. The grid connection is still sized to peak demand, the accumulator adds a large pressurised vessel to the site, and its pressure and output fall as the vessel empties.

An electric boiler with integrated thermal storage charges in the cheapest hours, stores the heat in a solid material, and raises steam when the process needs it. The storage medium varies: some systems use graphite, molten salt or steel, each with its own handling and safety considerations. The connection is sized to average load, peaks in steam demand are covered from the store, and the asset can earn the same flexibility revenue a battery would, without the battery. The Caldera Storage Boiler is in this category. It stores heat in inert aluminium-composite blocks, delivers saturated steam up to 16 barg at 94% round-trip efficiency, loses no capacity with cycling, and has a 20-year design life.

The boiler itself costs about the same in each case. The difference is in the grid connection upgrade, the transformers, the capacity charges and the storage, which is where most of the cost of an electrification project sits. The total cost of ownership also differs: maintenance, and whether any part of the system has to be replaced within the 20-year life of the boiler.